| Action Date | Action Description |
|---|---|
| Oct 24, 2022 | Maintenance Certification Request |
| Oct 25, 2022 | Administrative Review for Completeness |
| Oct 28, 2022 | Bio Team Review for Completeness |
| Oct 28, 2022 | Deficient Application - Owner Notification Sent |
| Jan 11, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Feb 10, 2023 | Deficiency Response Received |
| Feb 17, 2023 | Bio Team Review for Completeness |
| Feb 17, 2023 | Application Accepted |
| Feb 17, 2023 | Project Manager |
| Feb 28, 2023 | HPHC Historical Preservation No Effect |
| Feb 28, 2023 | HPHC Historical Preservation No Effect |
| Mar 08, 2023 | Biologist Report |
| Mar 10, 2023 | Permit Approved |
| Mar 13, 2023 | Permit Mailed |