| Action Date | Action Description |
|---|---|
| Feb 27, 1996 | Application Accepted |
| Feb 29, 1996 | Engineering Report |
| Feb 29, 1996 | Permit Approved |
| Feb 29, 1996 | Land Evidence Date |
| Dec 06, 2023 | Modification Request |
| Dec 08, 2023 | Administrative Review for Completeness |
| Dec 27, 2023 | Plans Received |
| Jan 03, 2024 | Eng Team Review for Completeness |
| Jan 03, 2024 | Project Manager |
| Jan 22, 2024 | 30 day Public Notice Issued |
| Jan 30, 2024 | HPHC Historical Preservation No Effect |
| Feb 09, 2024 | Dock/1.1.6 Review approval |
| Feb 22, 2024 | Public Notice End Date |
| Mar 29, 2024 | Engineering Report |
| Apr 15, 2024 | Typist for Processing |
| Apr 15, 2024 | Executive Sign Off |
| Apr 15, 2024 | Sent to Photo Copy |
| Apr 15, 2024 | Modification Approved |
| May 07, 2024 | Land Evidence Date |
| Jun 06, 2024 | Commencement of Work Notice received |