| Action Date | Action Description |
|---|---|
| Oct 28, 2009 | Assent Application Received |
| Oct 28, 2009 | Administrative Review for Completeness |
| Nov 03, 2009 | Team Review for Completeness |
| Nov 09, 2009 | Additional Information Received |
| Nov 10, 2009 | Application Accepted |
| Nov 10, 2009 | Category A* (Docks) |
| Nov 18, 2009 | 30 day Public Notice Issued |
| Nov 25, 2009 | HPHC Historical Preservation No Effect |
| Dec 18, 2009 | Public Notice End Date |
| Jan 15, 2010 | Biologist Report |
| Jan 21, 2010 | US Army Corp of Engineers Permit Date |
| Jan 26, 2010 | US Army Corps of Engineers Approval Received |
| Feb 11, 2010 | Dock Meeting -- Approval |
| Feb 11, 2010 | Dock Meeting Scheduled (Admin) |
| Feb 12, 2010 | Typist for Processing |
| Feb 12, 2010 | Executive Sign Off |
| Feb 12, 2010 | Sent to Photo Copy |
| Feb 12, 2010 | Permit Approved |
| Mar 29, 2010 | Commencement of Work Notice received |
| Jun 01, 2010 | Land Evidence Date |