| Action Date | Action Description |
|---|---|
| Jan 25, 2010 | Assent Application Received |
| Jan 25, 2010 | Administrative Review for Completeness |
| Jan 26, 2010 | Team Review for Completeness |
| Jan 26, 2010 | Team Review for Completeness |
| Jan 26, 2010 | Application Accepted |
| Jan 26, 2010 | Engineering Report |
| Jan 27, 2010 | Biologist Report |
| Jan 29, 2010 | Typist for Processing |
| Jan 29, 2010 | Executive Sign Off |
| Jan 29, 2010 | Sent to Photo Copy |
| Jan 29, 2010 | Permit Approved |
| Feb 11, 2010 | Land Evidence Date |
| Feb 12, 2010 | HPHC Historical Preservation No Effect |
| Oct 27, 2010 | Modification Request |
| Oct 27, 2010 | Administrative Review for Completeness |
| Oct 28, 2010 | Team Review for Completeness |
| Oct 29, 2010 | Biologist Report |
| Oct 29, 2010 | Engineering Report |
| Oct 29, 2010 | Team Review for Completeness |
| Nov 09, 2010 | Typist for Processing |
| Nov 09, 2010 | Executive Sign Off |
| Nov 09, 2010 | Sent to Photo Copy |
| Nov 09, 2010 | Modification Approved |
| Nov 22, 2010 | HPHC Historical Preservation No Effect |
| Nov 29, 2010 | Land Evidence Date |