| Action Date | Action Description |
|---|---|
| Aug 24, 2010 | Assent Application Received |
| Aug 24, 2010 | Administrative Review for Completeness |
| Aug 30, 2010 | Team Review for Completeness |
| Aug 30, 2010 | Team Review for Completeness |
| Aug 30, 2010 | Application Accepted |
| Sep 23, 2010 | HPHC Historical Preservation Comments/Concerns |
| Sep 24, 2010 | Public Notice End Date |
| Sep 24, 2010 | 30 day Public Notice Issued |
| Oct 25, 2010 | Additional Information Received |
| Oct 27, 2010 | Biologist Report |
| Oct 27, 2010 | Engineering Report |
| Oct 27, 2010 | Correspondence Received |
| Oct 29, 2010 | Supervisor Biologist SignOff |
| Oct 29, 2010 | Supervisor Engineer SignOff |
| Oct 29, 2010 | Executive Signoff of Staff Reports |
| Nov 15, 2010 | Ready to Schedule Semi-Monthly Meeting |
| Nov 15, 2010 | Mail Agenda Notice |
| Nov 23, 2010 | Council Approval Granted |
| Nov 23, 2010 | Semi-Monthly Meeting Date Scheduled |
| Nov 23, 2010 | Semi-Monthly Meeting Held |
| Dec 08, 2010 | Stipulation Package from Biologist |
| Dec 08, 2010 | Stipulation Package by Engineer |
| Dec 09, 2010 | Typist for Processing |
| Dec 09, 2010 | Permit Approved |
| Dec 13, 2010 | Legal Response/Decision |
| Dec 14, 2010 | Executive Sign Off |
| Dec 16, 2010 | Land Evidence Date |