| Action Date | Action Description |
|---|---|
| Mar 13, 2012 | Maintenance Certification Request |
| Mar 13, 2012 | Administrative Review for Completeness |
| Mar 21, 2012 | Team Review for Completeness |
| Mar 21, 2012 | Team Review for Completeness |
| Mar 21, 2012 | Deficient Application - Owner Notification Sent |
| Apr 24, 2012 | Deficiency Response Received |
| Apr 25, 2012 | Team Review for Completeness |
| Apr 25, 2012 | Team Review for Completeness |
| Apr 25, 2012 | Application Accepted |
| May 02, 2012 | Biologist Report |
| May 02, 2012 | Engineering Report |
| May 03, 2012 | Typist for Processing |
| May 03, 2012 | Permit Approved |
| May 03, 2012 | Pre-construction requirement by CRMC staff |
| May 04, 2012 | Executive Sign Off |
| May 04, 2012 | Sent to Photo Copy |
| May 25, 2012 | Land Evidence Date |
| Sep 21, 2012 | Note to File |