| Action Date | Action Description |
|---|---|
| Jul 30, 2021 | Assent Application Received |
| Aug 04, 2021 | Administrative Review for Completeness |
| Aug 19, 2021 | Bio Team Review for Completeness |
| Aug 19, 2021 | Deficient Application - Owner Notification Sent |
| Sep 27, 2021 | Deficiency Response Received |
| Sep 29, 2021 | Note to File |
| Nov 01, 2021 | Additional Information Requested from Applicant |
| Nov 04, 2021 | Plans Received |
| Nov 05, 2021 | Application Accepted |
| Nov 05, 2021 | Project Manager |
| Nov 05, 2021 | Bio Team Review for Completeness |
| Nov 23, 2021 | HPHC Review Pending |
| Nov 23, 2021 | HPHC Historical Preservation No Effect |
| Dec 17, 2021 | Plans Received |
| Dec 22, 2021 | Biologist Report |
| Dec 29, 2021 | Typist for Processing |
| Dec 29, 2021 | Executive Sign Off |
| Dec 29, 2021 | Sent to Photo Copy |
| Dec 29, 2021 | Permit Approved |
| Jan 07, 2022 | Permit Mailed |
| Jan 20, 2022 | Land Evidence Date |
| Jun 22, 2023 | Modification Request |
| Jun 27, 2023 | Administrative Review for Completeness |
| Jun 30, 2023 | Bio Team Review for Completeness |
| Jun 30, 2023 | Application Accepted |
| Jun 30, 2023 | Project Manager |
| Jul 31, 2023 | HPHC Historical Preservation No Effect |
| Aug 03, 2023 | Biologist Report |
| Aug 07, 2023 | Typist for Processing |
| Aug 07, 2023 | Executive Sign Off |
| Aug 07, 2023 | Sent to Photo Copy |
| Aug 07, 2023 | Permit Approved |
| Aug 09, 2023 | Permit Mailed |
| Sep 07, 2023 | Modification Approved |
| Oct 12, 2023 | Land Evidence Date |