| Action Date | Action Description |
|---|---|
| Jul 29, 2013 | Assent Application Received |
| Aug 02, 2013 | Administrative Review for Completeness |
| Aug 06, 2013 | Team Review for Completeness |
| Aug 06, 2013 | Team Review for Completeness |
| Aug 06, 2013 | Application Accepted |
| Aug 06, 2013 | Category B assigned |
| Aug 26, 2013 | 30 day Public Notice Issued |
| Sep 26, 2013 | Public Notice End Date |
| Nov 05, 2013 | Engineering Report |
| Jun 29, 2015 | Additional Information Received |
| Jul 14, 2015 | Mail Agenda Notice |
| Jul 23, 2015 | Biologist Report |
| Jul 27, 2015 | Semi-Monthly Meeting Postponed |
| Jul 28, 2015 | Semi-Monthly Meeting Date Scheduled |
| Aug 25, 2015 | Semi-Monthly Meeting Date Scheduled |
| Aug 25, 2015 | Council Approval Granted |
| Sep 14, 2015 | Stipulation Package from Biologist |
| Sep 14, 2015 | Stipulation Package by Engineer |
| Sep 14, 2015 | Legal Response/Decision |
| Sep 14, 2015 | 30 Day Appeal Notification to Owner |
| Sep 14, 2015 | Water Quality Certification |
| Sep 15, 2015 | Typist for Processing |
| Sep 15, 2015 | Executive Sign Off |
| Sep 15, 2015 | Sent to Photo Copy |
| Sep 15, 2015 | Permit Approved |
| Sep 22, 2015 | Land Evidence Date |