| Action Date | Action Description |
|---|---|
| Aug 30, 2023 | Dredge Application |
| Aug 30, 2023 | HPHC Historical Preservation No Effect |
| Sep 07, 2023 | Administrative Review for Completeness |
| Oct 27, 2023 | Application Accepted |
| Nov 01, 2023 | 15 day Public Notice Issued |
| Nov 16, 2023 | Public Notice End Date |
| Nov 29, 2023 | HPHC Historical Preservation No Effect |
| Dec 01, 2023 | Engineering Report |
| Dec 07, 2023 | Typist for Processing |
| Dec 07, 2023 | Executive Sign Off |
| Dec 07, 2023 | Sent to Photo Copy |
| Dec 07, 2023 | Permit Approved |
| Dec 08, 2023 | Permit Mailed |
| Dec 21, 2023 | US Army Corps of Engineers Approval Received |
| Jan 10, 2024 | Land Evidence Date |
| Feb 01, 2024 | US Army Corps of Engineers Approval Received |
| Apr 11, 2025 | Additional Information Received |
| Apr 23, 2025 | Correspondence Received |
| Jun 06, 2025 | CAD Cell Fee (initial) received |
| Jun 06, 2025 | CAD Cell Fee Due - initial (letter) |
| Jun 09, 2025 | CAD Cell Fee Due-Final |