| Action Date | Action Description | 
|---|---|
| Nov 05, 1991 | ISDS Approved | 
| Aug 23, 1993 | Application Accepted | 
| Sep 01, 1993 | Historical Preservation Approval Granted | 
| Sep 24, 1993 | Engineering Report | 
| Sep 28, 1993 | Biologist Report | 
| Oct 05, 1993 | Permit Approved | 
| Oct 12, 1993 | Land Evidence Date | 
| Aug 05, 2016 | Modification Request | 
| Aug 05, 2016 | Administrative Review for Completeness | 
| Aug 23, 2016 | Team Review for Completeness | 
| Aug 23, 2016 | Application Accepted | 
| Sep 07, 2016 | HPHC Historical Preservation No Effect | 
| Jan 11, 2017 | Biologist Report | 
| Jan 11, 2017 | Typist for Processing | 
| Jan 11, 2017 | Executive Sign Off | 
| Jan 11, 2017 | Sent to Photo Copy | 
| Jan 11, 2017 | Modification Approved | 
| Jan 20, 2017 | Land Evidence Date |