| Action Date | Action Description | 
|---|---|
| Sep 14, 2005 | Assent Application Received | 
| Sep 15, 2005 | Administrative Review for Completeness | 
| Sep 29, 2005 | Deficiency - Phone Call to Applicant/Owner | 
| Sep 29, 2005 | Deficient Application Picked Up | 
| Sep 29, 2005 | Deficiency Response Received | 
| Sep 29, 2005 | Team Review for Completeness | 
| Sep 29, 2005 | Application Accepted | 
| Oct 11, 2005 | Engineering Report | 
| Oct 11, 2005 | Typist for Processing | 
| Oct 11, 2005 | Permit Approved | 
| Oct 12, 2005 | Executive Sign Off | 
| Oct 12, 2005 | Sent to Photo Copy | 
| Oct 21, 2005 | Land Evidence Date |