| Action Date | Action Description | 
|---|---|
| Oct 21, 2009 | Assent Application Received | 
| Oct 23, 2009 | Administrative Review for Completeness | 
| Oct 28, 2009 | Team Review for Completeness | 
| Oct 28, 2009 | Team Review for Completeness | 
| Oct 28, 2009 | Application Accepted | 
| Nov 02, 2009 | Additional Information Received | 
| Nov 04, 2009 | Additional Information Received | 
| Nov 06, 2009 | Biologist Report | 
| Nov 06, 2009 | Engineering Report | 
| Nov 09, 2009 | HPHC Historical Preservation No Effect | 
| Nov 10, 2009 | Permit Approved | 
| Nov 10, 2009 | Typist for Processing | 
| Nov 12, 2009 | Executive Sign Off | 
| Nov 12, 2009 | Sent to Photo Copy | 
| Nov 18, 2009 | Land Evidence Date | 
| Jan 13, 2010 | Commencement of Work Notice received |