| Action Date | Action Description | 
|---|---|
| Jun 23, 2010 | Assent Application Received | 
| Jun 24, 2010 | Administrative Review for Completeness | 
| Jun 24, 2010 | Team Review for Completeness | 
| Jun 24, 2010 | Team Review for Completeness | 
| Jun 24, 2010 | Application Accepted | 
| Jul 16, 2010 | Plans Received | 
| Jul 26, 2010 | HPHC Historical Preservation No Effect | 
| Jul 28, 2010 | 30 day Public Notice Issued | 
| Aug 28, 2010 | Public Notice End Date | 
| Aug 31, 2010 | Public Notice End Date Extension Granted | 
| Sep 21, 2010 | Dock/1.1.6 Review approval | 
| Sep 24, 2010 | Correspondence Received | 
| Sep 27, 2010 | Biologist Report | 
| Sep 27, 2010 | Engineering Report | 
| Oct 01, 2010 | Typist for Processing | 
| Oct 01, 2010 | Category A* (Docks) | 
| Oct 01, 2010 | Permit Approved | 
| Oct 04, 2010 | Executive Sign Off | 
| Oct 04, 2010 | Sent to Photo Copy | 
| Oct 06, 2010 | Land Evidence Date | 
| Oct 19, 2010 | US Army Corp of Engineers Permit Date |