| Action Date | Action Description | 
|---|---|
| Jun 28, 2012 | Assent Application Received | 
| Jun 29, 2012 | Administrative Review for Completeness | 
| Jul 06, 2012 | Team Review for Completeness | 
| Jul 06, 2012 | Team Review for Completeness | 
| Jul 06, 2012 | Application Accepted | 
| Jul 24, 2012 | Additional Information Received | 
| Aug 01, 2012 | Additional Information Received | 
| Aug 02, 2012 | Typist for Processing | 
| Aug 02, 2012 | Biologist Report | 
| Aug 02, 2012 | Engineering Report | 
| Aug 02, 2012 | Permit Approved | 
| Aug 03, 2012 | Executive Sign Off | 
| Aug 03, 2012 | Sent to Photo Copy | 
| Aug 23, 2012 | Land Evidence Date |