| Action Date | Action Description | 
|---|---|
| Jan 30, 2015 | Assent Application Received | 
| Jan 30, 2015 | Administrative Review for Completeness | 
| Feb 26, 2015 | Team Review for Completeness | 
| Feb 26, 2015 | Deficient Application - Owner Notification Sent | 
| Mar 24, 2015 | Deficient Application Picked Up | 
| Mar 27, 2015 | Deficiency Response Received | 
| Apr 21, 2015 | Team Review for Completeness | 
| Apr 21, 2015 | Team Review for Completeness | 
| Apr 21, 2015 | Application Accepted | 
| May 27, 2015 | Biologist Report | 
| May 27, 2015 | Engineering Report | 
| May 28, 2015 | Typist for Processing | 
| May 28, 2015 | Executive Sign Off | 
| May 28, 2015 | Sent to Photo Copy | 
| May 28, 2015 | Permit Approved | 
| May 28, 2015 | HPHC Historical Preservation No Effect | 
| Jun 16, 2015 | Land Evidence Date |