| Action Date | Action Description | 
|---|---|
| Nov 03, 2015 | Maintenance Certification Request | 
| Nov 03, 2015 | Administrative Review for Completeness | 
| Nov 17, 2015 | Team Review for Completeness | 
| Nov 17, 2015 | Application Accepted | 
| Feb 01, 2016 | Letter of Support for Project | 
| Apr 11, 2016 | Mail Agenda Notice | 
| Apr 13, 2016 | Biologist Report | 
| Apr 13, 2016 | Biologist Report | 
| Apr 13, 2016 | Engineering Report | 
| Apr 13, 2016 | Geologist Report | 
| Apr 20, 2016 | Entry of Appearance Received | 
| Apr 22, 2016 | Continuance Requested | 
| Apr 22, 2016 | Continuance Requested by Objector Denied | 
| Apr 26, 2016 | Semi-Monthly Meeting Date Scheduled | 
| Jun 01, 2016 | Mail Agenda Notice | 
| Jun 09, 2016 | Entry of Appearance Received | 
| Jun 14, 2016 | Semi-Monthly Meeting Date Scheduled | 
| Jun 14, 2016 | Council Approval Granted | 
| Aug 01, 2016 | Stipulation Package by Engineer | 
| Aug 11, 2016 | Legal Response/Decision | 
| Feb 27, 2017 | Typist for Processing | 
| Mar 03, 2017 | Correspondence Mailed/Faxed/E-mailed | 
| May 11, 2017 | Correspondence Received | 
| May 15, 2017 | Correspondence Mailed/Faxed/E-mailed | 
| Nov 24, 2017 | Additional Information Received | 
| Mar 12, 2018 | Additional Information Received | 
| Sep 30, 2019 | Permit Approved | 
| Sep 30, 2019 | Executive Sign Off | 
| Sep 30, 2019 | Sent to Photo Copy | 
| Nov 13, 2019 | Land Evidence Date | 
| Dec 23, 2019 | Correspondence Received |