| Action Date | Action Description | 
|---|---|
| Jan 05, 2017 | Preliminary Determination Request (Coastal) | 
| Jan 05, 2017 | Application Accepted | 
| Jan 05, 2017 | Team Review for Completeness | 
| Jan 13, 2017 | HPHC Historical Preservation No Effect | 
| Jan 23, 2017 | Additional Information Received | 
| Feb 06, 2017 | Additional Information Received | 
| Feb 08, 2017 | Typist for Processing | 
| Feb 08, 2017 | Category A assigned | 
| Feb 08, 2017 | Executive Sign Off | 
| Feb 08, 2017 | Sent to Photo Copy | 
| Feb 08, 2017 | Permit Approved | 
| Feb 08, 2017 | Biologist Report | 
| Feb 16, 2017 | Land Evidence Date | 
| Mar 29, 2018 | Modification Request | 
| Mar 30, 2018 | Administrative Review for Completeness | 
| Mar 30, 2018 | Team Review for Completeness | 
| Mar 30, 2018 | Application Accepted | 
| Apr 06, 2018 | Biologist Report | 
| Apr 09, 2018 | Typist for Processing | 
| Apr 09, 2018 | Executive Sign Off | 
| Apr 09, 2018 | Sent to Photo Copy | 
| Apr 09, 2018 | Modification Approved | 
| Apr 11, 2018 | HPHC Historical Preservation No Effect | 
| Apr 23, 2018 | Land Evidence Date | 
| May 22, 2019 | Additional Information Received | 
| Jun 10, 2019 | Letter of Authorization | 
| Oct 21, 2019 | Modification Request | 
| Oct 22, 2019 | Eng Team Review for Completeness | 
| Oct 22, 2019 | Engineering Report | 
| Oct 22, 2019 | Biologist Report | 
| Oct 22, 2019 | Application Accepted | 
| Oct 22, 2019 | Typist for Processing | 
| Oct 22, 2019 | Executive Sign Off | 
| Oct 22, 2019 | Sent to Photo Copy | 
| Oct 22, 2019 | Modification Approved | 
| Oct 28, 2019 | Modification Request | 
| Oct 28, 2019 | Land Evidence Date | 
| Oct 31, 2019 | Bio Team Review for Completeness | 
| Nov 05, 2019 | Biologist Report | 
| Nov 05, 2019 | Typist for Processing | 
| Nov 05, 2019 | Executive Sign Off | 
| Nov 05, 2019 | Sent to Photo Copy | 
| Nov 05, 2019 | Modification Approved | 
| Nov 07, 2019 | HPHC Historical Preservation No Effect | 
| Jan 14, 2020 | Land Evidence Date | 
| Jul 09, 2021 | Modification Request | 
| Jul 12, 2021 | Administrative Review for Completeness | 
| Jul 14, 2021 | Eng Team Review for Completeness | 
| Jul 14, 2021 | Project Manager | 
| Jul 16, 2021 | Engineering Report | 
| Jul 16, 2021 | Letter of Authorization | 
| Jul 19, 2021 | Land Evidence Date | 
| Jul 21, 2021 | HPHC Review Pending | 
| Jul 21, 2021 | HPHC Historical Preservation No Effect | 
| Jan 27, 2022 | Modification Request | 
| Jan 31, 2022 | Administrative Review for Completeness | 
| Feb 11, 2022 | Project Manager | 
| Feb 11, 2022 | Bio Team Review for Completeness | 
| Feb 15, 2022 | Biologist Report | 
| Feb 15, 2022 | Typist for Processing | 
| Feb 15, 2022 | Executive Sign Off | 
| Feb 15, 2022 | Sent to Photo Copy | 
| Feb 15, 2022 | Letter of Authorization | 
| Feb 18, 2022 | Permit Mailed | 
| Apr 07, 2022 | Land Evidence Date |