| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Oct 28, 2019 | Assent Application Received | 
| Oct 28, 2019 | Administrative Review for Completeness | 
| Oct 30, 2019 | Bio Team Review for Completeness | 
| Oct 30, 2019 | Application Accepted | 
| Oct 31, 2019 | Category A* (Docks) | 
| Nov 07, 2019 | HPHC Historical Preservation No Effect | 
| Nov 07, 2019 | HPHC Review Pending | 
| Nov 21, 2019 | Plans Received | 
| Nov 26, 2019 | 30 day Public Notice Issued | 
| Dec 26, 2019 | Public Notice End Date | 
| Dec 26, 2019 | Comments Received | 
| Dec 26, 2019 | Objections/Comments Received | 
| Jan 09, 2020 | US Army Corps of Engineers Approval Received | 
| Jan 10, 2020 | Public Notice End Date Extension Granted | 
| Jan 13, 2020 | Objections/Comments Received | 
| May 19, 2020 | Comments Received | 
| Aug 17, 2020 | Additional Information Received | 
| Jan 24, 2022 | Plans Received | 
| Feb 10, 2022 | Biologist Report | 
| Feb 11, 2022 | Executive Signoff of Staff Reports | 
| Mar 01, 2022 | Mail Agenda Notice | 
| Mar 22, 2022 | Council Approval Granted | 
| Mar 22, 2022 | Semi-Monthly Meeting Date Scheduled | 
| Oct 12, 2022 | Legal Response/Decision | 
| Oct 13, 2022 | 30 Day Appeal Notification to Owner | 
| Oct 13, 2022 | Stipulation Package from Biologist | 
| Oct 19, 2022 | Typist for Processing | 
| Oct 19, 2022 | Executive Sign Off | 
| Oct 19, 2022 | Sent to Photo Copy | 
| Oct 19, 2022 | Permit Approved | 
| Oct 19, 2022 | Permit Mailed | 
| Oct 31, 2022 | Land Evidence Date | 
| Jun 16, 2023 | Commencement of Work Notice received |