| Action Date | Action Description | 
|---|---|
| Mar 02, 2020 | Maintenance Certification Request | 
| Mar 02, 2020 | Administrative Review for Completeness | 
| Mar 04, 2020 | Eng Team Review for Completeness | 
| Mar 04, 2020 | Application Accepted | 
| Sep 29, 2020 | Application Cancelled | 
| Sep 29, 2020 | Engineering Report | 
| Aug 18, 2021 | Biologist Report | 
| Aug 18, 2021 | Stipulation Package from Biologist | 
| Aug 20, 2021 | Typist for Processing | 
| Aug 20, 2021 | Executive Sign Off | 
| Aug 20, 2021 | Sent to Photo Copy | 
| Aug 20, 2021 | Permit Approved | 
| Aug 24, 2021 | Permit Mailed |