| Action Date | Action Description | 
|---|---|
| Dec 07, 2021 | Assent Application Received | 
| Dec 09, 2021 | Administrative Review for Completeness | 
| Dec 15, 2021 | Bio Team Review for Completeness | 
| Dec 15, 2021 | Application Accepted | 
| Dec 15, 2021 | Project Manager | 
| Dec 17, 2021 | Category A* (Docks) | 
| Jan 10, 2022 | 30 day Public Notice Issued | 
| Feb 10, 2022 | Public Notice End Date | 
| Feb 11, 2022 | Dock Meeting -- Approval | 
| Feb 14, 2022 | Biologist Report | 
| Feb 21, 2022 | Permit Approved | 
| Feb 21, 2022 | Typist for Processing | 
| Feb 21, 2022 | Executive Sign Off | 
| Feb 21, 2022 | Sent to Photo Copy | 
| Feb 23, 2022 | Permit Mailed | 
| Feb 25, 2022 | HPHC Review Pending | 
| Feb 25, 2022 | HPHC Historical Preservation No Effect | 
| Mar 03, 2022 | Land Evidence Date | 
| Oct 07, 2025 | Note to File |