| Action Date | Action Description | 
|---|---|
| Feb 03, 2022 | Maintenance Certification Request | 
| Feb 08, 2022 | Administrative Review for Completeness | 
| Feb 11, 2022 | Eng Team Review for Completeness | 
| Feb 15, 2022 | Deficient Application - Owner Notification Sent | 
| Mar 07, 2022 | Deficiency Response Received | 
| Mar 07, 2022 | Assent Application Received | 
| Mar 11, 2022 | Eng Team Review for Completeness | 
| Mar 31, 2022 | Eng Team Review for Completeness | 
| Mar 31, 2022 | Application Accepted | 
| Mar 31, 2022 | Project Manager | 
| Apr 01, 2022 | Category B assigned | 
| Apr 01, 2022 | 30 day Public Notice Issued | 
| Apr 11, 2022 | HPHC Review Pending | 
| Apr 11, 2022 | HPHC Historical Preservation No Effect | 
| May 01, 2022 | Public Notice End Date | 
| May 06, 2022 | Dock/1.1.6 Review approval | 
| May 12, 2022 | Engineering Report | 
| Jun 07, 2022 | Typist for Processing | 
| Jun 13, 2022 | Executive Sign Off | 
| Jun 13, 2022 | Sent to Photo Copy | 
| Jun 13, 2022 | Permit Approved | 
| Jun 13, 2022 | Permit Mailed | 
| Jun 21, 2022 | Land Evidence Date | 
| Sep 09, 2022 | Additional Information Received |