| Action Date | Action Description | 
|---|---|
| Mar 25, 2022 | Maintenance Certification Request | 
| Mar 31, 2022 | Administrative Review for Completeness | 
| Apr 06, 2022 | Eng Team Review for Completeness | 
| Apr 06, 2022 | Application Accepted | 
| Apr 07, 2022 | Project Manager | 
| May 03, 2022 | Engineering Report | 
| May 04, 2022 | Typist for Processing | 
| May 09, 2022 | Executive Sign Off | 
| May 09, 2022 | Sent to Photo Copy | 
| May 09, 2022 | Permit Approved | 
| May 09, 2022 | Permit Mailed | 
| May 11, 2022 | HPHC Historical Preservation No Effect | 
| May 11, 2022 | HPHC Review Pending |