| Action Date | Action Description | 
|---|---|
| May 05, 2022 | Maintenance Certification Request | 
| May 10, 2022 | Administrative Review for Completeness | 
| May 17, 2022 | Additional Information Requested from Applicant | 
| May 19, 2022 | Additional Information Received | 
| May 19, 2022 | Application Accepted | 
| May 19, 2022 | Project Manager | 
| May 19, 2022 | Bio Team Review for Completeness | 
| Jun 02, 2022 | HPHC Review Pending | 
| Jun 02, 2022 | HPHC Historical Preservation No Effect | 
| Sep 23, 2022 | Category A assigned | 
| Sep 23, 2022 | Typist for Processing | 
| Sep 23, 2022 | Executive Sign Off | 
| Sep 23, 2022 | Sent to Photo Copy | 
| Sep 23, 2022 | Permit Approved | 
| Sep 23, 2022 | Permit Mailed | 
| Sep 23, 2022 | Biologist Report | 
| Dec 08, 2022 | Correspondence Received | 
| Jan 09, 2023 | Comments Received |