| Action Date | Action Description | 
|---|---|
| Aug 02, 2023 | Assent Application Received | 
| Aug 04, 2023 | Administrative Review for Completeness | 
| Aug 08, 2023 | Bio Team Review for Completeness | 
| Aug 08, 2023 | Project Manager | 
| Aug 08, 2023 | Application Accepted | 
| Aug 25, 2023 | HPHC Historical Preservation No Effect | 
| Aug 31, 2023 | Biologist Report | 
| Sep 07, 2023 | Typist for Processing | 
| Sep 07, 2023 | Executive Sign Off | 
| Sep 07, 2023 | Sent to Photo Copy | 
| Sep 07, 2023 | Permit Approved | 
| Sep 12, 2023 | Permit Mailed | 
| Sep 28, 2023 | Land Evidence Date |