| Action Date | Action Description | 
|---|---|
| Oct 30, 2023 | Assent Application Received | 
| Nov 03, 2023 | Administrative Review for Completeness | 
| Nov 15, 2023 | Eng Team Review for Completeness | 
| Nov 15, 2023 | Application Accepted | 
| Nov 15, 2023 | Project Manager | 
| Nov 24, 2023 | HPHC Historical Preservation No Effect | 
| Dec 06, 2023 | 30 day Public Notice Issued | 
| Jan 06, 2024 | Public Notice End Date | 
| Jan 08, 2024 | Comments Received | 
| Feb 09, 2024 | Dock/1.1.6 Review approval | 
| Mar 06, 2024 | Engineering Report | 
| Mar 08, 2024 | Typist for Processing | 
| Mar 08, 2024 | Executive Sign Off | 
| Mar 08, 2024 | Sent to Photo Copy | 
| Mar 08, 2024 | Permit Approved | 
| Mar 12, 2024 | Permit Mailed | 
| Mar 27, 2024 | Land Evidence Date | 
| Dec 24, 2024 | Commencement of Work Notice received |