| Action Date | Action Description | 
|---|---|
| Nov 13, 2024 | Assent Application Received | 
| Nov 18, 2024 | Administrative Review for Completeness | 
| Jan 06, 2025 | Bio Team Review for Completeness | 
| Jan 07, 2025 | Deficient Application - Owner Notification Sent | 
| Jan 09, 2025 | Additional Information Received | 
| Jan 27, 2025 | Deficiency Response Received | 
| Feb 07, 2025 | Correspondence Mailed/Faxed/E-mailed | 
| Aug 19, 2025 | Application Accepted | 
| Aug 19, 2025 | Project Manager | 
| Aug 19, 2025 | Bio Team Review for Completeness | 
| Aug 25, 2025 | HPHC Historical Preservation No Effect | 
| Sep 08, 2025 | Biologist Report | 
| Sep 10, 2025 | Typist for Processing | 
| Sep 10, 2025 | Executive Sign Off | 
| Sep 10, 2025 | Sent to Photo Copy | 
| Sep 10, 2025 | Permit Approved | 
| Sep 10, 2025 | Dock Post-Construction Certification by Engineer Required. | 
| Sep 12, 2025 | Permit Mailed | 
| Sep 16, 2025 | Land Evidence Date | 
| Oct 29, 2025 | Commencement of Work Notice received |