| Action Date | Action Description | 
|---|---|
| Nov 26, 2024 | Maintenance Certification Request | 
| Dec 02, 2024 | Administrative Review for Completeness | 
| Dec 26, 2024 | Eng Team Review for Completeness | 
| Dec 26, 2024 | Deficient Application - Owner Notification Sent | 
| Jan 17, 2025 | Deficiency Response Received | 
| Jan 17, 2025 | CHA Worksheet received | 
| Jan 28, 2025 | Application Accepted | 
| Jan 28, 2025 | Project Manager | 
| Jan 28, 2025 | Eng Team Review for Completeness | 
| Feb 13, 2025 | HPHC Historical Preservation No Effect | 
| May 12, 2025 | Additional Information Received | 
| May 12, 2025 | Engineering Report | 
| May 14, 2025 | Typist for Processing | 
| May 14, 2025 | Executive Sign Off | 
| May 14, 2025 | Sent to Photo Copy | 
| May 14, 2025 | Permit Approved | 
| May 16, 2025 | Permit Mailed | 
| May 21, 2025 | Land Evidence Date |