| Action Date | Action Description | 
|---|---|
| May 05, 2025 | CHA Worksheet received | 
| May 05, 2025 | Assent Application Received | 
| May 07, 2025 | Administrative Review for Completeness | 
| May 09, 2025 | Eng Team Review for Completeness | 
| May 09, 2025 | Project Manager | 
| May 09, 2025 | Application Accepted | 
| May 20, 2025 | 30 day Public Notice Issued | 
| Jun 13, 2025 | HPHC Historical Preservation No Effect | 
| Jun 20, 2025 | Public Notice End Date | 
| Jun 24, 2025 | Comments Received | 
| Jun 26, 2025 | Public Notice End Date Extension Granted | 
| Jul 01, 2025 | Comments Received | 
| Jul 03, 2025 | Executive Signoff of Staff Reports | 
| Jul 03, 2025 | Engineering Report | 
| Jul 29, 2025 | Mail Agenda Notice | 
| Aug 26, 2025 | Semi-Monthly Meeting Date Scheduled | 
| Sep 04, 2025 | Mail Agenda Notice | 
| Sep 09, 2025 | Semi-Monthly Meeting Date Scheduled | 
| Sep 11, 2025 | US Army Corps of Engineers Approval Received |