| Action Date | Action Description | 
|---|---|
| Sep 28, 2005 | Assent Application Received | 
| Sep 29, 2005 | Administrative Review for Completeness | 
| Oct 03, 2005 | Deficient Application - Owner Notification Sent | 
| Oct 07, 2005 | Deficiency Response Received | 
| Oct 13, 2005 | Team Review for Completeness | 
| Oct 13, 2005 | Application Accepted | 
| Oct 18, 2005 | Engineering Report | 
| Oct 19, 2005 | Typist for Processing | 
| Oct 19, 2005 | Permit Approved | 
| Oct 20, 2005 | Executive Sign Off | 
| Oct 20, 2005 | Sent to Photo Copy | 
| Oct 20, 2005 | Land Evidence Date | 
| Oct 25, 2005 | HPHC Historical Preservation No Effect |