| Action Date | Action Description | 
|---|---|
| May 19, 2006 | Assent Application Received | 
| May 22, 2006 | Administrative Review for Completeness | 
| May 23, 2006 | Team Review for Completeness | 
| May 23, 2006 | Fee Waiver Granted | 
| May 23, 2006 | Application Accepted | 
| Jun 08, 2006 | Joint Public Notice | 
| Jul 01, 2006 | Historical Preservation Conditional Approval | 
| Jul 07, 2006 | Correspondence Received | 
| Jul 08, 2006 | Public Notice End Date | 
| Jul 10, 2006 | Correspondence Received | 
| Jul 21, 2006 | Additional Information Requested from Applicant | 
| Aug 07, 2006 | Correspondence Received | 
| Aug 09, 2006 | Plans Received | 
| Aug 11, 2006 | Additional Information Received | 
| Aug 22, 2006 | Water Quality Certification | 
| Aug 22, 2006 | Public Hearing Notices Mailed | 
| Aug 28, 2006 | Additional Information Received | 
| Aug 31, 2006 | Additional Information Received | 
| Sep 05, 2006 | Engineering Report | 
| Sep 05, 2006 | Engineering Report | 
| Sep 06, 2006 | Biologist Report | 
| Sep 06, 2006 | Executive Sign Off | 
| Sep 12, 2006 | Semi-Monthly Meeting Postponed | 
| Sep 12, 2006 | Semi-Monthly Meeting Date Scheduled | 
| Sep 12, 2006 | Public Hearing Scheduled | 
| Sep 19, 2006 | Council Approval Granted | 
| Sep 19, 2006 | Ready to Schedule Semi-Monthly Meeting | 
| Sep 19, 2006 | Semi-Monthly Meeting Held | 
| Sep 20, 2006 | Typist for Processing | 
| Sep 20, 2006 | Stipulation Package by Engineer | 
| Sep 20, 2006 | Stipulation Package from Biologist | 
| Sep 20, 2006 | Permit Approved | 
| Sep 20, 2006 | Executive Sign Off | 
| Sep 20, 2006 | Sent to Photo Copy | 
| Oct 05, 2006 | Land Evidence Date | 
| Nov 14, 2006 | Legal Response/Decision | 
| Feb 02, 2007 | Phone Call | 
| Mar 05, 2007 | Assent Correction Mailed | 
| Mar 21, 2007 | Land Evidence Date | 
| Apr 25, 2007 | HPHC Historical Preservation No Effect | 
| Apr 10, 2017 | Correspondence Mailed/Faxed/E-mailed |