| Action Date | Action Description | 
|---|---|
| Sep 15, 2008 | Assent Application Received | 
| Sep 17, 2008 | Administrative Review for Completeness | 
| Sep 19, 2008 | Team Review for Completeness | 
| Sep 19, 2008 | Team Review for Completeness | 
| Sep 19, 2008 | Application Accepted | 
| Oct 03, 2008 | HPHC Historical Preservation No Effect | 
| Oct 29, 2008 | Additional Information Requested from Applicant | 
| Dec 04, 2008 | Additional Information Received | 
| Jan 14, 2009 | Typist for Processing | 
| Jan 14, 2009 | Executive Sign Off | 
| Jan 14, 2009 | Sent to Photo Copy | 
| Jan 14, 2009 | Permit Approved | 
| Jan 14, 2009 | Biologist Report | 
| Feb 26, 2009 | Land Evidence Date | 
| Aug 23, 2010 | Commencement of Work Notice received |