| Action Date | Action Description | 
|---|---|
| Mar 02, 2011 | Assent Application Received | 
| Mar 02, 2011 | Administrative Review for Completeness | 
| Mar 09, 2011 | Team Review for Completeness | 
| Mar 09, 2011 | Team Review for Completeness | 
| Mar 09, 2011 | Application Accepted | 
| Mar 23, 2011 | HPHC Historical Preservation No Effect | 
| May 31, 2011 | Correspondence Received | 
| Feb 14, 2012 | 30 Day Appeal Notification to Owner | 
| Feb 14, 2012 | 30-Day Notification of Cancellation letter | 
| Feb 16, 2012 | Certified Receipt Received | 
| Mar 16, 2012 | Correspondence Received | 
| Apr 19, 2012 | Plans Received | 
| Apr 19, 2012 | Entry of Appearance Received | 
| May 04, 2012 | Additional Information Received | 
| May 11, 2012 | 30 day Public Notice Issued | 
| Jun 11, 2012 | Public Notice End Date | 
| Jun 20, 2012 | US Army Corps of Engineers Approval Received | 
| Jul 12, 2012 | Biologist Report | 
| Jul 12, 2012 | Engineering Report | 
| Jul 13, 2012 | Supervisor Biologist SignOff | 
| Jul 13, 2012 | Supervisor Engineer SignOff | 
| Feb 13, 2013 | Executive Signoff of Staff Reports | 
| Apr 11, 2013 | Ready to Schedule Semi-Monthly Meeting | 
| Apr 11, 2013 | Mail Agenda Notice | 
| Apr 15, 2013 | Continuance Requested | 
| Apr 15, 2013 | Continuance request by applicant granted by Director | 
| Apr 19, 2013 | Ready to Schedule Semi-Monthly Meeting | 
| Apr 19, 2013 | Mail Agenda Notice | 
| Jun 07, 2013 | Continued application | 
| Jun 11, 2013 | Semi-Monthly Meeting Date Scheduled | 
| Mar 14, 2016 | Plans Received | 
| Mar 24, 2016 | 30 day Public Notice Issued | 
| Mar 29, 2016 | Additional Information Requested from Applicant | 
| Apr 21, 2016 | Plans Received | 
| Apr 25, 2016 | Public Notice End Date | 
| May 13, 2016 | Dock Meeting Scheduled (Admin) | 
| May 19, 2016 | US Army Corps of Engineers Approval Received | 
| Jun 09, 2016 | Plans Received | 
| Jun 15, 2016 | Biologist Report | 
| Jun 16, 2016 | Engineering Report | 
| Jun 22, 2016 | Typist for Processing | 
| Jun 22, 2016 | Executive Sign Off | 
| Jun 22, 2016 | Sent to Photo Copy | 
| Jun 22, 2016 | Permit Approved | 
| Jul 12, 2016 | Land Evidence Date | 
| Dec 29, 2016 | Commencement of Work Notice received |