| Action Date | Action Description | 
|---|---|
| May 07, 2013 | Dredge Application | 
| May 07, 2013 | Administrative Review for Completeness | 
| May 09, 2013 | Team Review for Completeness | 
| May 09, 2013 | Application Accepted | 
| May 22, 2013 | Joint Public Notice | 
| May 22, 2013 | Category B assigned | 
| Jun 22, 2013 | Public Notice End Date | 
| Jun 25, 2013 | HPHC Historical Preservation No Effect | 
| Jul 17, 2013 | DEM Dredge Permit | 
| Jul 24, 2013 | Biologist Report | 
| Jul 24, 2013 | Dredge Report | 
| Jul 26, 2013 | Executive Signoff of Staff Reports | 
| Aug 05, 2013 | Mail Agenda Notice | 
| Aug 15, 2013 | US Army Corps of Engineers Approval Received | 
| Aug 27, 2013 | Semi-Monthly Meeting Postponed | 
| Aug 27, 2013 | Ready to Schedule Semi-Monthly Meeting | 
| Aug 27, 2013 | Mail Agenda Notice | 
| Aug 27, 2013 | Semi-Monthly Meeting Date Scheduled | 
| Sep 10, 2013 | Council Approval Granted | 
| Sep 10, 2013 | Semi-Monthly Meeting Date Scheduled | 
| Sep 10, 2013 | Semi-Monthly Meeting Held | 
| Sep 26, 2013 | 30 Day Appeal Notification to Owner | 
| Sep 26, 2013 | Legal Response/Decision | 
| Oct 02, 2013 | Dredge Permit Issued | 
| Oct 02, 2013 | Typist for Processing | 
| Oct 02, 2013 | Stipulation Package from Biologist | 
| Oct 02, 2013 | Stipulation Package by Engineer | 
| Oct 03, 2013 | Executive Sign Off | 
| Oct 03, 2013 | Sent to Photo Copy | 
| Jan 12, 2015 | Correspondence Mailed/Faxed/E-mailed | 
| Jan 15, 2015 | CAD Cell Fee Due-Final |