| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Sep 13, 2021 | Assent Application Received | 
| Sep 16, 2021 | Administrative Review for Completeness | 
| Sep 17, 2021 | Bio Team Review for Completeness | 
| Sep 17, 2021 | Application Accepted | 
| Sep 20, 2021 | Project Manager | 
| Sep 20, 2021 | Category A* (Docks) | 
| Sep 30, 2021 | 30 day Public Notice Issued | 
| Oct 04, 2021 | HPHC Review Pending | 
| Oct 04, 2021 | HPHC Historical Preservation No Effect | 
| Oct 30, 2021 | Public Notice End Date | 
| Dec 17, 2021 | Biologist Report | 
| Dec 20, 2021 | Typist for Processing | 
| Dec 20, 2021 | Executive Sign Off | 
| Dec 20, 2021 | Sent to Photo Copy | 
| Dec 20, 2021 | Permit Approved | 
| Dec 21, 2021 | Permit Mailed | 
| Jan 05, 2022 | Land Evidence Date |