| Action Date | Action Description | 
|---|---|
| Oct 30, 2023 | Assent Application Received | 
| Nov 03, 2023 | Administrative Review for Completeness | 
| Nov 07, 2023 | Bio Team Review for Completeness | 
| Nov 07, 2023 | Application Accepted | 
| Nov 07, 2023 | Project Manager | 
| Nov 24, 2023 | HPHC Historical Preservation No Effect | 
| Dec 18, 2023 | 30 day Public Notice Issued | 
| Jan 18, 2024 | Public Notice End Date | 
| Feb 09, 2024 | Dock/1.1.6 Review approval | 
| Mar 20, 2024 | Biologist Report | 
| Mar 22, 2024 | Additional Information Received | 
| Mar 25, 2024 | Typist for Processing | 
| Mar 25, 2024 | Executive Sign Off | 
| Mar 25, 2024 | Sent to Photo Copy | 
| Mar 25, 2024 | Permit Approved | 
| Apr 02, 2024 | Permit Mailed | 
| Aug 01, 2024 | Dock Plate re-issue | 
| Aug 01, 2024 | Land Evidence Date | 
| Aug 21, 2024 | Commencement of Work Notice received | 
| Oct 17, 2024 | Dock Post-Construction Certification by Engineer received. |