| Action Date | Action Description | 
|---|---|
| Monitoring Report | |
| Dec 20, 2023 | Buffer Zone Management Application Received | 
| Dec 27, 2023 | Administrative Review for Completeness | 
| Jan 19, 2024 | Bio Team Review for Completeness | 
| Jan 22, 2024 | Deficient Application - Owner Notification Sent | 
| Feb 16, 2024 | Deficiency Response Received | 
| Feb 22, 2024 | Additional Information Received | 
| Mar 13, 2024 | Application Accepted | 
| Mar 13, 2024 | Project Manager | 
| Mar 13, 2024 | Bio Team Review for Completeness | 
| Apr 09, 2024 | HPHC Historical Preservation No Effect | 
| Apr 26, 2024 | Additional Information Requested from Applicant | 
| May 30, 2024 | Additional Information Received | 
| Jul 16, 2024 | Correspondence Mailed/Faxed/E-mailed | 
| Jul 26, 2024 | Plans Received | 
| Aug 14, 2024 | Biologist Report | 
| Aug 19, 2024 | Typist for Processing | 
| Aug 19, 2024 | Executive Sign Off | 
| Aug 19, 2024 | Sent to Photo Copy | 
| Aug 19, 2024 | Permit Approved | 
| Aug 20, 2024 | Permit Mailed | 
| Sep 04, 2024 | Land Evidence Date | 
| Oct 01, 2024 | Commencement of Work Notice received |