| Action Date | Action Description | 
|---|---|
| Jan 14, 2025 | Maintenance Certification Request | 
| Jan 23, 2025 | Administrative Review for Completeness | 
| Jan 24, 2025 | Bio Team Review for Completeness | 
| Jan 30, 2025 | Additional Information Received | 
| Jan 31, 2025 | Application Accepted | 
| Jan 31, 2025 | Project Manager | 
| Feb 12, 2025 | HPHC Historical Preservation No Effect | 
| Feb 28, 2025 | Biologist Report | 
| Mar 04, 2025 | Typist for Processing | 
| Mar 04, 2025 | Executive Sign Off | 
| Mar 04, 2025 | Sent to Photo Copy | 
| Mar 04, 2025 | Permit Approved | 
| Mar 06, 2025 | Permit Mailed | 
| Mar 25, 2025 | Land Evidence Date | 
| May 05, 2025 | Letter of Authorization |