| Action Date | Action Description |
|---|---|
| Mar 24, 2006 | Assent Application Received |
| Mar 27, 2006 | Administrative Review for Completeness |
| Mar 29, 2006 | Deficient Application - Owner Notification Sent |
| Apr 06, 2006 | Deficient Application Picked Up |
| Jul 31, 2006 | Deficiency Response Received |
| Aug 18, 2006 | Team Review for Completeness |
| Aug 18, 2006 | Application Accepted |
| Aug 21, 2006 | 30 day Public Notice Issued |
| Sep 21, 2006 | Public Notice End Date |
| Sep 28, 2006 | Typist for Processing |
| Sep 28, 2006 | Executive Sign Off |
| Sep 28, 2006 | Sent to Photo Copy |
| Sep 28, 2006 | Permit Approved |
| Sep 28, 2006 | Biologist Report |
| Sep 28, 2006 | Engineering Report |
| Oct 12, 2006 | Land Evidence Date |
| Oct 16, 2006 | US Army Corp of Engineers Permit Date |
| Oct 19, 2006 | US Army Corps of Engineers Approval Received |
| Oct 20, 2006 | Water Quality Certification |
| Nov 21, 2006 | Commencement of Work Notice received |