| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Mar 26, 2025 | Assent Application Received | 
| Apr 01, 2025 | Administrative Review for Completeness | 
| Apr 02, 2025 | Bio Team Review for Completeness | 
| Apr 02, 2025 | Project Manager | 
| Apr 02, 2025 | Application Accepted | 
| Apr 10, 2025 | HPHC Historical Preservation No Effect | 
| Apr 28, 2025 | Plans Received | 
| Jul 10, 2025 | Plans Received | 
| Jul 16, 2025 | Additional Information Received | 
| Jul 16, 2025 | Comments Received | 
| Jul 16, 2025 | Dock/1.1.6 Review approval | 
| Jul 29, 2025 | 30 day Public Notice Issued | 
| Aug 05, 2025 | Comments Received | 
| Aug 07, 2025 | US Army Corps of Engineers Project Number received. | 
| Aug 28, 2025 | Objections/Comments Received | 
| Aug 28, 2025 | Objections/Comments Received | 
| Aug 29, 2025 | Public Notice End Date | 
| Sep 03, 2025 | Response to Objections received. | 
| Sep 05, 2025 | Dock/1.1.6 Review approval | 
| Sep 08, 2025 | Response to Objections received. | 
| Sep 15, 2025 | Objection withdrawal received | 
| Sep 17, 2025 | Biologist Report | 
| Sep 17, 2025 | Engineering Report | 
| Sep 22, 2025 | Typist for Processing | 
| Sep 22, 2025 | Executive Sign Off | 
| Sep 22, 2025 | Sent to Photo Copy | 
| Sep 22, 2025 | Permit Approved | 
| Sep 22, 2025 | Dock Post-Construction Certification by Engineer Required. | 
| Sep 25, 2025 | Permit Mailed | 
| Oct 15, 2025 | Land Evidence Date |