| Action Date | Action Description | 
|---|---|
| HPHC Review Pending | |
| Jun 11, 2025 | Assent Application Received | 
| Jul 02, 2025 | Administrative Review for Completeness | 
| Jul 10, 2025 | Bio Team Review for Completeness | 
| Jul 10, 2025 | Project Manager | 
| Jul 10, 2025 | Application Accepted | 
| Jul 17, 2025 | Biologist Report | 
| Jul 23, 2025 | Typist for Processing | 
| Jul 23, 2025 | Executive Sign Off | 
| Jul 23, 2025 | Sent to Photo Copy | 
| Jul 23, 2025 | Permit Approved | 
| Jul 25, 2025 | Permit Mailed | 
| Aug 18, 2025 | Land Evidence Date | 
| Aug 18, 2025 | Assent Requirement | 
| Sep 02, 2025 | Commencement of Work Notice received |