| Action Date | Action Description | 
|---|---|
| Jul 25, 2006 | Assent Application Received | 
| Jul 26, 2006 | Administrative Review for Completeness | 
| Jul 28, 2006 | Team Review for Completeness | 
| Jul 28, 2006 | Application Accepted | 
| Aug 10, 2006 | Historical Preservation Conditional Approval | 
| Oct 06, 2006 | Plans Received | 
| Oct 16, 2006 | Correspondence Received | 
| Oct 31, 2006 | Historical Preservation Conditional Approval | 
| Oct 31, 2006 | Engineering Report | 
| Oct 31, 2006 | HPHC Historical Preservation No Effect | 
| Nov 01, 2006 | Typist for Processing | 
| Nov 01, 2006 | Executive Sign Off | 
| Nov 01, 2006 | Sent to Photo Copy | 
| Nov 01, 2006 | Permit Approved | 
| Nov 17, 2006 | Commencement of Work Notice received | 
| Nov 22, 2006 | Land Evidence Date |