| Action Date | Action Description | 
|---|---|
| Nov 28, 2006 | Assent Application Received | 
| Nov 29, 2006 | Administrative Review for Completeness | 
| Nov 30, 2006 | Team Review for Completeness | 
| Nov 30, 2006 | Application Accepted | 
| Nov 30, 2006 | Category B assigned | 
| Dec 06, 2006 | HPHC Historical Preservation No Effect | 
| Dec 26, 2006 | 30 day Public Notice Issued | 
| Jan 10, 2007 | Correspondence Received | 
| Jan 18, 2007 | Correspondence Mailed/Faxed/E-mailed | 
| Jan 18, 2007 | Correspondence Received | 
| Jan 31, 2007 | Engineering Report | 
| Feb 15, 2007 | Correspondence Received | 
| Feb 16, 2007 | Public Notice End Date | 
| Mar 12, 2007 | US Army Corp of Engineers Permit Date | 
| Mar 14, 2007 | US Army Corps of Engineers Approval Received | 
| Mar 29, 2007 | Additional Information Received | 
| Apr 02, 2007 | Correspondence Mailed/Faxed/E-mailed | 
| Apr 20, 2007 | Additional Information Received | 
| Apr 23, 2007 | Biologist Report | 
| Apr 23, 2007 | Engineering Report | 
| Apr 24, 2007 | Dock Meeting Scheduled (Admin) | 
| Apr 26, 2007 | Stipulation Package by Engineer | 
| Apr 26, 2007 | Stipulation Package from Biologist | 
| Apr 27, 2007 | Typist for Processing | 
| Apr 27, 2007 | Executive Sign Off | 
| Apr 27, 2007 | Sent to Photo Copy | 
| Apr 27, 2007 | Permit Approved | 
| May 11, 2007 | Land Evidence Date |