| Action Date | Action Description |
|---|---|
| Mar 14, 2007 | Assent Application Received |
| Mar 15, 2007 | Administrative Review for Completeness |
| Mar 15, 2007 | Team Review for Completeness |
| Mar 15, 2007 | Team Review for Completeness |
| Mar 15, 2007 | Application Accepted |
| Mar 15, 2007 | Category A* (Docks) |
| Mar 22, 2007 | HPHC Historical Preservation No Effect |
| May 18, 2007 | Plans Received |
| Jul 16, 2007 | Plans Received |
| Jul 16, 2007 | Additional Information Received |
| Jul 17, 2007 | 30 day Public Notice Issued |
| Aug 03, 2007 | HPHC Historical Preservation No Effect |
| Aug 17, 2007 | Public Notice End Date |
| Nov 02, 2007 | Correspondence Received |
| Nov 19, 2007 | US Army Corp of Engineers Permit Date |
| Nov 23, 2007 | US Army Corps of Engineers Approval Received |
| Dec 03, 2007 | Plans Received |
| Dec 04, 2007 | Biologist Report |
| Dec 04, 2007 | Engineering Report |
| Dec 05, 2007 | Supervisor Biologist SignOff |
| Dec 05, 2007 | Supervisor Engineer SignOff |
| Dec 05, 2007 | Executive Signoff of Staff Reports |
| Dec 27, 2007 | Ready to Schedule Semi-Monthly Meeting |
| Dec 27, 2007 | Mail Agenda Notice |
| Jan 02, 2008 | Mail Agenda Notice |
| Jan 08, 2008 | Semi-Monthly Meeting Date Scheduled |
| Jan 15, 2008 | Council Approval Granted |
| Jan 15, 2008 | Semi-Monthly Meeting Date Scheduled |
| Feb 13, 2008 | Plans Received |
| Feb 18, 2008 | Correspondence Mailed/Faxed/E-mailed |
| Feb 28, 2008 | Plans Received |
| Mar 11, 2008 | Typist for Processing |
| Mar 11, 2008 | Executive Sign Off |
| Mar 11, 2008 | Sent to Photo Copy |
| Mar 11, 2008 | Stipulation Package from Biologist |
| Mar 11, 2008 | Stipulation Package by Engineer |
| Mar 11, 2008 | Legal Response/Decision |
| Mar 11, 2008 | Permit Approved |
| May 19, 2008 | Land Evidence Date |