| Action Date | Action Description | 
|---|---|
| Sep 04, 2007 | Assent Application Received | 
| Sep 05, 2007 | Administrative Review for Completeness | 
| Sep 05, 2007 | Application Accepted | 
| Sep 13, 2007 | HPHC Historical Preservation No Effect | 
| Sep 25, 2007 | Typist for Processing | 
| Sep 25, 2007 | Executive Sign Off | 
| Sep 25, 2007 | Sent to Photo Copy | 
| Sep 25, 2007 | Permit Approved | 
| Sep 25, 2007 | Engineering Report | 
| Oct 03, 2007 | Land Evidence Date | 
| Feb 07, 2008 | Modification Request | 
| Feb 12, 2008 | Administrative Review for Completeness | 
| Feb 12, 2008 | Team Review for Completeness | 
| Feb 21, 2008 | HPHC Historical Preservation No Effect | 
| Feb 27, 2008 | Typist for Processing | 
| Feb 27, 2008 | Executive Sign Off | 
| Feb 27, 2008 | Sent to Photo Copy | 
| Feb 27, 2008 | Modification Approved | 
| Feb 27, 2008 | Engineering Report | 
| Mar 06, 2008 | Land Evidence Date |