| Action Date | Action Description | 
|---|---|
| Nov 01, 2007 | Assent Application Received | 
| Nov 05, 2007 | Plans Received | 
| Nov 06, 2007 | Team Review for Completeness | 
| Nov 06, 2007 | Application Accepted | 
| Nov 06, 2007 | Administrative Review for Completeness | 
| Nov 19, 2007 | HPHC Historical Preservation No Effect | 
| Apr 14, 2008 | Typist for Processing | 
| Apr 14, 2008 | Executive Sign Off | 
| Apr 14, 2008 | Sent to Photo Copy | 
| Apr 14, 2008 | Permit Approved | 
| Apr 14, 2008 | Biologist Report | 
| Apr 21, 2008 | Land Evidence Date | 
| Apr 23, 2008 | Commencement of Work Notice received |