| Action Date | Action Description | 
|---|---|
| Jan 05, 2015 | Assent Application Received | 
| Jan 05, 2015 | Administrative Review for Completeness | 
| Jan 07, 2015 | Team Review for Completeness | 
| Jan 07, 2015 | Application Accepted | 
| Jan 20, 2015 | 30 day Public Notice Issued | 
| Jan 21, 2015 | Plans Received | 
| Feb 02, 2015 | HPHC Historical Preservation No Effect | 
| Feb 19, 2015 | US Army Corps of Engineers Approval Received | 
| Feb 20, 2015 | Objections/Comments Received | 
| Feb 20, 2015 | Public Notice End Date | 
| Mar 23, 2015 | Correspondence Received | 
| Apr 07, 2015 | Correspondence Mailed/Faxed/E-mailed | 
| Apr 09, 2015 | 30 day Public Notice Issued | 
| Apr 09, 2015 | Plans Received | 
| Apr 13, 2015 | Plans Received | 
| Apr 24, 2015 | Plans Received | 
| May 09, 2015 | Public Notice End Date | 
| Jun 30, 2015 | US Army Corps of Engineers Approval Received | 
| Jul 08, 2015 | Plans Received | 
| Aug 14, 2015 | Plans Received | 
| Aug 19, 2015 | Engineering Report | 
| Aug 24, 2015 | Typist for Processing | 
| Aug 25, 2015 | Executive Sign Off | 
| Aug 25, 2015 | Sent to Photo Copy | 
| Aug 25, 2015 | Permit Approved | 
| Sep 08, 2015 | Land Evidence Date | 
| Dec 30, 2015 | Category A* (Docks) |