| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jul 19, 2017 | Assent Application Received | 
| Jul 19, 2017 | Administrative Review for Completeness | 
| Jul 26, 2017 | Team Review for Completeness | 
| Jul 26, 2017 | Deficient Application - Owner Notification Sent | 
| Aug 21, 2017 | Deficient Application Picked Up | 
| Mar 09, 2018 | Deficiency Response Received | 
| Mar 15, 2018 | Team Review for Completeness | 
| Mar 15, 2018 | Additional Information Received | 
| Mar 15, 2018 | Application Accepted | 
| Apr 06, 2018 | HPHC Historical Preservation No Effect | 
| Jul 12, 2018 | Plans Received | 
| Sep 17, 2018 | 30 day Public Notice Issued | 
| Oct 17, 2018 | Public Notice End Date | 
| Oct 19, 2018 | Biologist Report | 
| Oct 23, 2018 | Dock Meeting Scheduled (Admin) | 
| Oct 23, 2018 | Dock/1.1.6 Review approval | 
| Oct 24, 2018 | Stipulation Package from Biologist | 
| Oct 24, 2018 | Typist for Processing | 
| Oct 24, 2018 | Executive Sign Off | 
| Oct 24, 2018 | Sent to Photo Copy | 
| Oct 24, 2018 | Permit Approved | 
| Oct 30, 2018 | Land Evidence Date |