| Action Date | Action Description | 
|---|---|
| Oct 26, 2018 | Assent Application Received | 
| Oct 29, 2018 | Administrative Review for Completeness | 
| Oct 29, 2018 | Team Review for Completeness | 
| Oct 29, 2018 | Application Accepted | 
| Nov 23, 2018 | Biologist Report | 
| Nov 26, 2018 | Typist for Processing | 
| Nov 26, 2018 | Executive Sign Off | 
| Nov 26, 2018 | Sent to Photo Copy | 
| Nov 26, 2018 | Permit Approved | 
| Nov 27, 2018 | HPHC Historical Preservation No Effect | 
| Feb 19, 2019 | Land Evidence Date | 
| Feb 21, 2019 | Modification Request | 
| Feb 22, 2019 | Administrative Review for Completeness | 
| Mar 06, 2019 | Additional Information Received | 
| Mar 08, 2019 | Team Review for Completeness | 
| Mar 11, 2019 | Application Accepted | 
| Mar 20, 2019 | HPHC Historical Preservation No Effect | 
| Mar 20, 2019 | HPHC Review Pending | 
| Apr 03, 2019 | Biologist Report | 
| Apr 04, 2019 | Typist for Processing | 
| Apr 04, 2019 | Executive Sign Off | 
| Apr 04, 2019 | Sent to Photo Copy | 
| Apr 04, 2019 | Modification Approved | 
| Aug 05, 2019 | Land Evidence Date |