| Action Date | Action Description | 
|---|---|
| Jun 08, 2022 | Assent Application Received | 
| Jun 13, 2022 | Administrative Review for Completeness | 
| Jun 27, 2022 | Bio Team Review for Completeness | 
| Jun 27, 2022 | Deficient Application - Owner Notification Sent | 
| Oct 19, 2022 | Deficiency Response Received | 
| Oct 26, 2022 | Bio Team Review for Completeness | 
| Oct 26, 2022 | Application Accepted | 
| Oct 26, 2022 | Project Manager | 
| Nov 02, 2022 | Additional Information Received | 
| Jan 03, 2023 | HPHC Historical Preservation No Effect | 
| Jan 09, 2023 | Biologist Report | 
| Jan 11, 2023 | Typist for Processing | 
| Jan 11, 2023 | Executive Sign Off | 
| Jan 11, 2023 | Sent to Photo Copy | 
| Jan 11, 2023 | Permit Approved | 
| Jan 12, 2023 | Permit Mailed | 
| Feb 08, 2023 | Land Evidence Date | 
| Jun 21, 2023 | Commencement of Work Notice received |