| Action Date | Action Description | 
|---|---|
| Mar 17, 2004 | Application Accepted | 
| Mar 17, 2004 | Category B assigned | 
| Mar 31, 2004 | Historical Preservation Approval Granted | 
| Apr 02, 2004 | 30 day Public Notice Issued | 
| Aug 18, 2004 | Engineering Report | 
| Sep 10, 2004 | Biologist Report | 
| Sep 24, 2004 | Biologist Report | 
| Sep 28, 2004 | Meeting Held | 
| Sep 28, 2004 | Semi-Monthly Meeting Held | 
| Sep 28, 2004 | Council Approval Granted | 
| Mar 29, 2005 | Stipulation Package from Biologist | 
| Mar 30, 2005 | Stipulation Package by Engineer | 
| Mar 31, 2005 | Typist for Processing | 
| Mar 31, 2005 | Executive Sign Off | 
| Mar 31, 2005 | Sent to Photo Copy | 
| Mar 31, 2005 | Permit Approved | 
| Apr 12, 2005 | Biologist Report | 
| Apr 12, 2005 | Legal Response/Decision | 
| Apr 13, 2005 | Plans Received | 
| Apr 13, 2005 | Modification Approved | 
| Apr 26, 2005 | Land Evidence Date | 
| Mar 26, 2007 | Modification Request | 
| Mar 27, 2007 | Administrative Review for Completeness | 
| Apr 02, 2007 | Additional Information Received | 
| Apr 03, 2007 | Modification Canceled | 
| Apr 03, 2007 | Team Review for Completeness |